Peebles water works building makes 200 mile journey from the Highlands

The six-month countdown to completion for the new multimillion water treatment works in Peebles has started, and Scottish Water are sharing never-before-seen images of the building taking shape after making its journey from the highlands.

The works, which was constructed off site by Ross-Shire Engineering at their factory in Muir of Ord, was transported nearly 200 miles by road in 17 sections. It is the largest of its kind in the UK and is full of new water treatment technologies.

By building the works off-site, the team have been able to cut down the construction time, reduce the amount of construction traffic through the town and make savings on carbon.

Daniel Sutherland from Ross-Shire Engineering said: “This is the largest transportable treatment works ever built in the UK and getting it to site from our factory up North has been a real logistics challenge. It is brilliant to finally see the building in situ and to start the six-month countdown to it supplying water to the town.”

The countdown to the completion of the project has started

The works, which is supplied with water from Megget Reservoir 18km away, houses four CeraMac Membranes which are able to effectively and efficiently treat large volumes of water to the highest standards. These membranes work by pushing the water through tiny holes which are many times smaller than a human hair, helping them to catch the smallest impurities in the water.

Keeping the carbon emissions down has been a key priority for the project team. Rather than removing soil from the site during construction, it has been used to help the works blend into the landscape and has helped to reduce the amount of site traffic. On the building’s roof, 50MWh of solar panels have been installed to help power the site.

John Shaw, Project Manager for the works, said: “The innovative technologies which have gone into this building are very impressive. From the construction methods, to the treatment equipment and the renewables, this has been one of the most exciting projects I have been involved in. I can’t wait to see it up and running.”

Over the next six months, the outside of the works will slowly blend into its surroundings through the planting of trees, wildflowers and further landscaping. Inside the building, engineers will be getting the new works ready to seamlessly switch over supply to customers in the area.

NEWS CATEGORIES

LATEST NEWS

Environment Agency Chief Regulator calls for environmental regulation framework to be reformed

Environment Agency Chief Regulator, Dr Jo Nettleton, has called for the environmental regulation framework to be reformed in order to help better protect people...

Norfolk farmer fined for taking water during summer drought

Following a successful prosecution by the Environment Agency, a Norfolk farmer with a history of environmental offending has been fined for taking and using...

Turning the tide on saltmarsh loss in the River Dart

The work to repair and revive rare intertidal habitat is being done by several organisations including the Environment Agency, Bioregional Learning Centre (BLC), Dart...

Thames Water installs brand new storm tank at Bentley Sewage Treatment Works as part of £6 million investment 

Thames Water has announced the installation of a new storm tank as part of a £6 million upgrade taking place at Bentley STW, to...