Ballyronan to benefit from new £5m Wastewater Treatment Works

NI Water has announced the completion of a £5m programme of work to provide Ballyronan with a modern new wastewater treatment facility.

The existing treatment works, which was constructed in the 1970s off the Shore Road in Ballyronan, remained in operation throughout the 18-month contract, while the new infrastructure was installed at the same site, ensuring no disruption to customers’ wastewater services during construction.

Tzvetelina Bogoina, NI Water’s Director of Infrastructure Delivery said:

“NI Water is delighted to announce the completion of a significant £5m programme of work, which will directly benefit customers in the Ballyronan area by delivering key economic and environmental benefits.

“These essential improvements will help support local development and help improve water quality in Lough Neagh for many years to come.”

The NI Water Project Team mark the completion of Ballyronan Wastewater Treatment Works.
The NI Water Project Team mark the completion of Ballyronan Wastewater Treatment Works.

The work included the installation of state-of-the-art, fully enclosed, treatment tanks, along with advanced electrical and mechanical systems to provide a robust wastewater treatment solution.

Chair of Mid Ulster District Council, Councillor Eugene McConnell added:

“I was delighted to have the opportunity to visit the Ballyronan site recently to view the improvements first hand.

“This is a great investment in the delivery of essential new wastewater infrastructure for the local community and it was great to meet the NI Water team on the ground, as well as local companies involved in the construction of the upgrade: Coalisland-based GEDA Construction and Newry-based Water Solutions Ireland.”

NI Water Derrychrin Project Team: A nearby Wastewater Treatment Works at Derrychrin was also recently completed.
NI Water Derrychrin Project Team: A nearby Wastewater Treatment Works at Derrychrin was also recently completed.

GEDA Construction was the main contractor for the 18-month contract, while Water Solutions Ireland completed extensive mechanical and electrical installation at the site. RPS Group provided technical support for the project.

The provision of a new treatment works at Ballyronan follows the completion of a similar state-of-the-art facility at nearby Derrychrin – by Castlederg-based Lowry Building & Civil Engineering as part of the DLJ consortium – also managed by RPS.

SourceNI Water

NEWS CATEGORIES

LATEST NEWS

Ofwat approves funding for London Water Recycling scheme

Ofwat has approved funding for the London Water Recycling scheme to continue and progress to gate four as a single solution, with Teddington Direct...

CCW responds to Ofwat’s latest amendment to the Customer Protection Code of Practice

The Consumer Council for Water (CCW) is concerned that Ofwat’s decision to change the billing accuracy requirement in the Customer Protection Code of Practice (CPCoP) will...

Four bills that could have an impact on the water and wastewater industry scheduled for second reading in Parliament today

Four bills that could have an impact on the water and wastewater industry are scheduled for their second reading in Parliament today (11 July...

OEP highlights the critical role of inspections in environmental regulation in England

A new report by the Office for Environmental Protection (OEP) identifies the crucial role inspections must play in environmental regulation in England and calls...