QEII reservoir back in action and refilled with equivalent of 8,000 Olympic pools of water

A £25 million investment project to help protect London’s water supply for the next decade has been successfully completed ahead of schedule in Walton-on-Thames.

Work to drain the Queen Elizabeth II reservoir, which stores around ten per cent of all of London’s pre-treated drinking water, began in April 2021 so that essential maintenance could be carried out to help protect the capital’s water supply. The reservoir was not due to be refilled until this summer, but after maintenance work finished ahead of schedule, the reservoir has been gradually filling up since November. From March 1st has officially returned to servicing and supplying water to the nearby Hampton water treatment works.

The reservoir is one of the largest in the region and when full holds 19,623 million litres of water – the equivalent of around 8,000 Olympic swimming pools.

While it was drained engineers relined the two tunnels which feed water into the reservoir from the River Thames and carries it from there to the nearby treatment works, from where it is pumped to homes across London. The relining has strengthened the tunnels to prevent any future leaks.

Rachel Whiteman, Thames Water’s project manager, said: “The QEII plays a really important role in the supply of top-quality drinking water for millions of people across Surrey and London, so we’re delighted we’ve been able to carry out the vital maintenance work and refill it ahead of schedule. It’s been a huge effort by the whole team and we’d like to thank everyone in the area for their patience while we temporarily had a road closed and had construction vehicles coming on and off the site.”

NEWS CATEGORIES

LATEST NEWS

Government Taskforce meets on Merseyside to bolster nation’s flood resilience

Bolstering the nation’s resilience to flooding, including in Merseyside, was top of the agenda as the Government’s national Floods Resilience Taskforce convened in Aintree...

Independent Networks Association says Corry Review’s silence on New Appointments and Variations (NAVs) is a significant omission

The Independent Networks Association (INA) has said that although it welcomes the publication of Delivering economic growth and nature recovery: An independent review of...

Increased confidence amongst project profession for UK achieving 2050 net zero targets, new survey shows

A new survey suggests that over half (52%) of project professionals are very confident that the UK will meet its net zero targets by...

United Living strengthens water business with acquisition of Peter Duffy Ltd

United Living Group, solutions provider to the UK’s critical infrastructure, has announced the acquisition of Peter Duffy Ltd, a civil engineering contractor specialising in...